One of the territorial generating companies approached RUSTRADE LLC with a question: is it possible to install a steam turbine with a generator into an existing heat network.
The TGC produced superheated steam, then reduced it to the parameters required by the end customer. Ideally, it was necessary to obtain 2.5 MW power to fully cover their electricity needs.