Oil Extraction Plant

Installation of 5 MW turbogenerator unit at oil extraction plant

The oil extraction plant approached RUSTRADE LLC with the task of proposing the most economically viable energy generation solution through sunflower husk utilization.

Sunflower husk with extremely unstable sales brings many problems and huge costs for removal and disposal.

1

Provide production with electricity without gas costs

2

Husk disposal without costs

Based on the survey and calculations performed by RUSTRADE LLC specialists, the following solution was proposed: construction of an energy center based on two husk-gas steam boilers and a 5 MW condensing steam turbine with extraction.

Technical and economic project indicators:

# Parameter Before project After project
1 TGU power, MW 5
2 Boiler equipment
Boiler type 2 husk-gas steam boilers
Fuel Sunflower husk
3 Operating parameters
Operating hours per year, h 8000
Electricity tariff, RUB/kWh 7.3 0 (own generation)
4 Project cost, RUB 750,000,000
5 Electricity savings, RUB/year 0 292,000,000
6 Husk disposal savings, RUB/year 0 30,000,000
7 Total effect, RUB/year 0 322,000,000
8 Payback period, years < 2.32
1

RUSTRADE LLC solution meets the customer's goal of providing electrical power for own production

2

The customer completely solved the husk disposal issue

3

Effect from energy center construction is 322 million RUB/year

4

Project payback period – less than 2.32 years

0 B ₽
Economic effect over 30 years
< 10 years
Project payback period

Get Consultation

Our specialists will help you choose the optimal solution for your enterprise and calculate the economic effect

All Questions & Answers

Answers to frequently asked questions about turbogenerator units, delivery times and cooperation terms

Go to FAQ
Rustrade

Energy solutions that pay off

Home Engineering Turbines Turbogenerators Blades Oil Coolers Condensers About Cases News & Articles FAQ Cooperation Contacts